Shrewsberry was part of the Construction Management team for the Denver International Airport (DEN) Hotel and Transit Center.
The south terminal and landside expansion included the construction of a structural foundation system, five level podium, nine level hotel structure, public transit center, DIA train platform and canopy and the level 5 plaza and plaza canopies. Work also included the extension of the AGTS structure from the face of the existing terminal into the new public transit center, extension of the existing baggage handling system from the terminal into the podium and the integration of the existing tent roof structure with the new construction.
Shrewsberry provided fast-track preconstruction services, and led the quality control program for the construction management team. The scopes of work included site/civil, concrete, enclosures, structural steel and welding, interiors, mechanical, electrical, plumbing, and commissioning.